design stage

2 moment(s) that assert this concept — showing 1–2 of 2

single sourceRests on a single channel — treat as a lead, verify independently
↣ how this spread over time →
provenance — click a node to open its encoding unit
[1] 1[2] 1
showing 2 of 2 moments
1 Smart Fox · youtube · en
1The total number of possible outcomes for the project duration is nine, calculated as three possible design stage durations multiplied by two possible construction stage durations.
“the total number of outcomes in the sample space will be three times three nine”
spoken · 356s · 2022-09-30
1 Smart Fox · youtube · en
2The project's design stage has three possible durations (two, three, or four months), and the construction stage has two possible durations (six, seven, or eight months).
“three so N1 is three the number of possible outcomes in the design stage and two is three the number of possible outcomes in the construction stage”
spoken · 373s · 2022-09-30