1 The total number of possible outcomes for the project duration is nine, calculated as three possible design stage durations multiplied by two possible construction stage durations.
“the total number of outcomes in the sample space will be three times three nine”
spoken · 356s · 2022-09-30 · en · 1 Smart Fox · BUA 220 Chapter 4: Introduction to Probability Lecture Video