soil removal

5 moment(s) that assert this concept — showing 1–5 of 5

moderateTwo independent sources — corroborated, but not broadly
↣ how this spread over time →
provenance — click a node to open its encoding unit
[1] Practical[2] Practical[3] Practical[4] Practical[5] The
showing 5 of 5 moments
Practical Engineering · youtube · en
1Under excavation reduces tower tilt by removing soil beneath the foundation in a controlled manner.
“If they couldn't get the soil below the tower to consolidate, they could just take some out. And again, they would need to test it out first.”
spoken · 450s · 2023-12-19
Practical Engineering · youtube · en
2A test footing was constructed in 1995 to evaluate under excavation techniques using incline drills and hollow stem augers.
“in 1995, they built to large concrete footing on the piazza grounds not far from the tower. Then they used incline drills to bore underneath the footing and gradually remove some of the underlying soil.”
spoken · 480s · 2023-12-19
Practical Engineering · youtube · en
3In 2000, 41 holes were drilled to remove 38 cubic meters of soil, reducing the tower's tilt and stabilizing it over a year.
“Starting in 2000, 41 holes were drilled to slowly tilt the tower upright. Over the course of a year, 38 cubic meters of soil were removed from below the tower, roughly 70 tons.”
spoken · 600s · 2023-12-19
Practical Engineering · youtube · en-US
4Driven piles are noisy, disruptive, and can cause ground heave due to lack of soil removal during installation.
“they can cause the ground to heave because you’re not removing any soil while you force them into the subsurface.”
spoken · 524s · 2024-07-02
The Build — How The World is Made · youtube · en
5After construction, drills are used to disrupt the soil, which is then removed by autonomous vehicles, leaving a ready-made tunnel with reusable pipes for maintenance.
“once the structure is complete drills are brought back in to disrupt the soil which is then removed by autonomous vehicles leaving behind a ready-made tunnel then other than a bit of final preparation to the walls and of course the laying of the road or rail line the tunnel is ready to go and those ball pipes can even be reused for maintenance”